Mole Home Services were contacted by returning client to help assist with the installation of a new watermain. The property was undergoing extensive renovation and the old lead pipework was still present in the property.
We completed a remote survey and arranged for a date to complete the works to suit the building schedule.
After a last-minute change of pipe size on site, our engineers installed 14 meters of 32mm MDPE Waterpipe. This was connected to the existing 32mm in the footpath and terminated with a 32mm Stop tap internally. The internal plumber on site was then all set to complete the rest of the pipework inside the property.
All areas externally were reinstated, and the building works were able to continue.